September 8, 2010

Site Progress Meeting 8th September 2010

Plot A
Plot A

The apartments on Plot A, ie those in Blocks A, B, G and H are now finished and fully snagged internally. We are waiting for delivery of the last pieces of expansion joint materials to enable the rest of the communal external area to be completed.

The site was due for handover by the construction company on 1st September but due to a few items still to finish off externally, as well as waiting for the electricity authority to finish the testing and commissioning of the electricity supply to each apartment, we will now take possession of the site on 5th October. Delivery of Plot B (comprising Blocks C, D, E and F) will be on 20th October. This new handover timetable does not affect the delivery of the apartments which are finished and undergoing final snagging ahead of the delivery to clients between 15th September and 15th November.

Kitchen of Block D Townhouse
Kitchen of Block D Townhouse

In the communal external spaces, the Gripstone areas are almost completed and the wooden decking around the pools has begun to be installed.

Installing the wooden decking
Installing the wooden decking

All garden areas have now been planted and the artificial grass installed between Blocks A, H, G and B which gives a cool, calm feeling to the resort.

View from ground floor apartment in B block

View from ground floor apartment in B block

View of resort from upper floor of Block H
View of Block B

View of resort from upper floor of Block H

View of Block B

The utility companies have finished the installation of water and electricity connections around the development so the road construction is now underway. With so much messy work going on around the edges of the resort to complete the roads and pathways we are delaying filling the pools until the end of the month.

Laying out the visitor car park next to Block G

Finishing the main car park of the Spa building

We spent time this week with potential operators of the restaurant and supermarket and also continued with the interviews for resort staff. The Spa building continues to shape up well.

Spa building reception
Spa building reception
Roof top café bar
View from the gym
Roof top café bar

View from the gym


Sound proofed ceiling of the dance studio
Dominic and Joanne in the TV room
Sound proofed ceiling of the dance studio

Dominic and Joanne in the TV room


View of plot B from Spa building

View of plot B from Spa building

Back of Block H

Back of Block H

The underground car parks are finished as are the ramps in and out. The fire shutters will be installed next and the individual car park space markings.

Underground car park entrance
Underground car park exit

Underground car park entrance

Underground car park exit
Underground car park

Underground car park

The next site meeting will take place on Tuesday 5th October.